Submitted by admin on Wed, 06/05/2015 - 15:20
Status:
Complete
Project TimeFrame:
Sep 2008 to Sep 2011
Budget:
USD 256.000
Sector:
Lingkungan
Related-Area:
Gorontalo
Nusa Tenggara Barat
Nusa Tenggara Timur
Papua
Papua Barat
Sulawesi Utara
Link Terkait:
Contact(s) Details:
Renadi Budiman
Source: http://pid.adb.org/pid/LoanView.htm?projNo=34100&seqNo=01&typeCd=3
Deskripsi Project:
The Project will expand renewable energy use and thereby limit emission of greenhouse gases. Construction and commissioning of hydropower, geothermal, and transmission lines for power evacuation.
RED 1- Merasap, Lobong and Mongango mini-hydro (all core)
RED 2 - Ndungga (core), Santong and Prafi (noncore)
RED 3 - Lahendong II (noncore)
RED 4 - Poigar 2 hydropower (noncore) --- replaced with Lahendong IV GPP
RED 5 - Genyem hydro power (noncore)
RED 6 - Amai and Tatui (noncore)
RED 7 - Ulumbu mini-geothermal proj. (noncore)
RED 8 - Lahendong IV (noncore)
Pemerintah Mitra:
Organisasi Pendana: